314 m² maßgeschneiderte Leichtstahlvilla mit Pool an Hanglage, bemessen nach NTC 2018 Erdbebennormen und geliefert mit A.TR (0 % Zoll).
The property was situated on a 32-degree steep hillside with narrow mountain access roads overlooking Lake Como. Conventional reinforced concrete construction would have required extensive hillside excavation, heavy tower cranes, and months of disruptive road closures.
SerVilla engineered a high-tensile cold-formed steel structure weighing only 16.4 tons (70% lighter than concrete). The framing members were pre-engineered to transport lengths and delivered by medium rigid trucks. A local 4-man construction team guided by one SerVilla bilingual supervisor erected the full structural frame and weather-tight shell in just 12 working days without heavy cranes.
From initial 3D BIM engineering in Istanbul to jobsite handover in Bellagio.
BIM 3D modeling in Vertex BD and 3D finite-element stress analysis. Full structural calculation book (Relazione di Calcolo) and foundation reaction tables delivered to client's Italian civil engineer for Genio Civile filing.
High-speed roll-forming of all S350GD galvanized profiles with 100% individual inkjet part numbering and sequential package strapping for steep site delivery.
Issuance of official A.TR Movement Certificate (0% EU customs duty). Loading onto standard mega curtainsider truck, Ro-Ro sailing from Pendik to Trieste, and direct highway haulage to Como.
Chemical anchor bolt setting on concrete slab, ground floor wall assembly, floor diaphragm joists, and roof truss erection overseen on site by a bilingual SerVilla structural engineer.
Transparent delineation between factory-engineered elements and local on-site trade coordination.
Building on a steep slope over Lake Como seemed impossible with local concrete contractors. SerVilla delivered the entire frame in days, the statics passed Genio Civile without a single objection, and the thermal insulation in winter is extraordinary.
Frequently asked engineering, customs, and assembly questions regarding the Bellagio delivery.
Ja. Der Statikbericht wurde exakt nach NTC 2018 und den Eurocodes 1, 3 und 8 mit seismischer Spektralanalyse aufbereitet und vom Genio Civile ohne Rückfragen genehmigt.
Die Stahlprofile wurden passgenau auf Transportlängen vorgefertigt und mit wendigen LKWs angeliefert. Durch das 70 % geringere Gewicht erfolgte die Montage in 12 Tagen ohne schwere Baukräne.
Ja. Die Kombination aus 140 mm Steinwolle im Profilhohlraum und 80 mm externem WDVS erreicht einen U-Wert von 0,15 W/m²K und übertrifft die Vorgaben der Lombardei.
Discover other high-performance steel frame homes engineered and delivered across Europe.
322 m² exklusives Alpenwohnhaus mit prüffähiger Statik nach DIN EN 1993-1-3, 3,5 kN/m² Schneelastbemessung und KfW-40-Wärmedämmverbundsystem.
229 m² moderne Ferienvilla auf Kreta: Ausgelegt für extreme Erdbebenzonen (EAK Zone III), meersalzresistent beschichtet und in 3 Tagen per Inselfähre geliefert.
181 m² Leichtstahl-Bausatz nach britischen Baustandards (BS EN 1993, Part L) mit 0 % Zoll über das UK-Türkei-Freihandelsabkommen.
Upload your architectural drawings (PDF/DWG/IFC) or select a SerVilla design to receive an itemized budgetary quotation, Eurocode statics review, and direct shipping estimate.